STC Signed Nehe SNCR Equipment Purchase Contract

Time:2016-12-27

Nehe Waste To Energy Project is financed and owned by Qidi Sound Enviornmental Resource Incorporation Limited. The planned location of this project is at No. 2 area of municipal landfill which is in the east of Nahe city, Heilongjiang province. The distance from site to downtown is around 8.5 km. One grate furnance will be used in this project with the total municipal waste disposal capacity of 600 ton/day.

STC will supply one set of SNCR system for the off gas teatment. Meanwhile, STC will also provide design, manufacturing, installation, commissioning and trial operation. The design operational hour is no less than 8000 hours/year.